Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook

Si necesita esta informaciĂłn traducida al español, comunĂ­quese con nuestra oficina al (616)530-7260. 

City Projects

Week of July 20, 2026

CITY OF WYOMING PROJECTS

Burton Street Reconstruction - Burlingame to Clyde Park (including work on Osmer) (Anlaan Corp)

Contractor is working in the area of Burton between Kamp Avenue and Clyde Park Avenue. Contractor has completed watermain work within this area. They are working on grading the road and will start pouring concrete this week.

Concrete work is completed on Osmer Ave. Paving the first course of asphalt was delayed from last week and is expected this week instead.

Boone Avenue Watermain Reconstruction - Lacrosse to 36th Street (Wyoming Exc)

Contractor is working on concrete and lawn restoration and will continue through the week.

56th Street and Byron Center Dual Left Turn Lane - (Brenner Exc)

Northbound left lane on Byron Center will remain closed for several weeks. Contractor will be pouring concrete for the dual left turn lanes this week. Contractor will also continue utility and concrete work on the north side of 56th Street, from Byron Center to the west.

Wyoming Local Resurfacing Program - (Michigan Paving and Materials, Inc)

Contractor is removing and replacing concrete on Havana Ave between Lee Street and Chicago Drive this week.

Prairie Parkway Reconstruction – Wentworth to Michael - (Wyoming Exc)

Contractor is working on “crush and shape” of the old pavement in the area between Michael and Burlingame. They are working on the north half of the road first and plan to have that side paved by next week. Traffic flow is in the east bound direction only until the north half is paved.

Cape Seal Pavement Preservation

The City's cape seal pavement preservation street surface treatment for the 2026 season is tentatively scheduled for the week of July 20.

A cape seal is a two-part pavement preservation process that improves, preserves, and extends the useful service life of an existing street surface.

Schedule

The project will last about two weeks, but is subject to change depending on weather, availability of materials,  or unforeseen emergencies. Each street takes approximately two days.

Work will be completed Monday through Saturday, from 7 am to 9 pm. Expect “no parking” signs on applicable street segments. To avoid any inconvenience as work takes place, residents are encouraged to park on adjacent streets via on-street parking.

Project Locations 

Street 

Limits 

Wyoming 

Lee to Chicago Dr 

Collingwood 

Lee to Chicago Dr 

Burton 

Greenfield to Collingwood 

Ithaca 

Greenfield to Collingwood 

Avon 

Porter to North end of street 

Melvin/Ithaca  

Greenfield to East end of street 

Lee 

Sharon to Avon 

Meurs Ct 

Avon to West end of street 

Wyoming 

28th to Porter 

Boulevard 

Wrenwood to Porter  

Wrenwood                       

Wyoming to Meyer  

Avon

28th to Porter 

Meyer  

28th to Porter 

 

PRIVATE DEVELOPMENT PROJECTS

3738 – 52nd Street - Salmon’s View Residential Development (Excel Exc)

Contractor is working on Site Grading. Utility work in 52nd Street is scheduled to start on July 27 and will require 52nd Street to be closed for approximately 2 weeks.

300 36th Street – Corewell Heath (Pioneer Construction)

Contractor had delayed pavement markings and new schedule is unknown. This work will require 1 lane in each direction to be closed.