Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of July 14, 2025
CITY OF WYOMING PROJECTS​
Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)
Phase 1 is complete except for minor clean-up and top course paving.
Mainline watermain is complete in phase 2. Contractor is working on installing hydrants and watermain to side streets. We anticipate being ready to test phase 2 watermain next week.

Division Ave Phasing Plan
Wyoming City Center Bridge Project (Anlaan Construction)
The contractor is working on the pedestrian bridge over 28th Street. Contractor is working on installation of architectural panels and lighting components. Periodic lane closures on 28th Street will be required for this work.
Wyoming City Center Trail Project (Katerberg-Verhage and Strain Electric)
Trail work continues in Pinery Park. HAWK signal work will continue in late summer when strain poles are available.
PRIVATE DEVELOPMENT PROJECTS
Benteler Automotive Fireline (4011 Stafford Ave., SW) – Dan Hoe Excavating
Utility work is complete. A small amount of concrete work remains to be completed in the ROW.
Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.
Right Turn lane and traffic signal on 36th Street not yet scheduled.
Godwin Mercado (36th St. Market) Watermain – GVL Excavating
Final drive approach on 36th Street has been installed.
Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating
Base course of asphalt this has been completed. Top course of asphalt won’t be scheduled until Consumers Energy pole is relocated. This is anticipated to be several weeks out.
Malta Woods (N. off 56th, E of Wilson) – Fischer Idema
Storm sewer connection in 56th Street is not yet scheduled and is dependent on fiber optic lines being relocated by AT&T. This schedule is at least 2-3 weeks out.
Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating
Contractor is removing excess soil from the plat and working on placing gravel for new streets.
Courtyard at Wyoming (4051 Del Mar Drive) – Excel Excavating
Watermain connection is planned for this week.