Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on contruction activity. Below you'll find updates for city projects, plats, and site developments. Check back each week for updates or follow us on Facebook

 
Week of June 15, 2020

City Projects

Clyde Park Watermain, 26th St to 36th St (Nagel Construction)

Contractor completed the final pavement repairs last week and is complete except for pavement markings.  Markings will be painted next week to finalize the project. 

2019 Wyoming Resurfacing (Reith Riley)

All areas are complete with the exception of final restoration work.  Contractor anticipates completing all restoration this week to finalize the project.

2020 Wyoming Resurfacing

Prepping project for bidding mid-July.

2020 Watermain Project – Buchanan Ave, 36th St to 40th St

Project has been bid and awarded to Bultsma Excavating.  Anticipate starting in July.

2020 Watermain Project – Denwood & Marquette (Bultsma Excavating)

Contractor is continuing to lay new watermain working to the east along Marquette Park.  Watermain is expected to be placed by the end of the week and ready for testing.  The westerly section of watermain passed testing from Burlingame to Federal and will be ready to start water services.

DTE completed the gas main renewal on Denwood last week in preparation for the watermain project. 

Byron Center Resurfacing, 44th Street to M-6 (Michigan Paving and Materials, Inc)

Project has been bid at MDOT.  Preconstruction meeting scheduled for Monday this week.

Frog Hollow M-6 Trail Connector (Nagel Construction)

Contractor has graded sand subbase for trail connection.  Contractor will start concrete path Tuesday.

New Burlingame Pump Station and Tank Restoration

The welding contractor has cut a door into the East steel tank to gain interior access.  They have started to repair deficiencies in the steel interior and exterior shell.  Additionally, the contractor is making structural repairs to the interior of the tank.  This work will continue for the next couple of weeks.

 

Plats

None currently active.

 

Site Developments

Clyde Park 2-Hotels – Traffic signal modification work later this summer.

MHV PUD Update Plan (ODP) – Granger updating traffic impact study.  Reviewing parking requirements.

Springs Apartments – Contractor working on building construction. 

28 West Apartments – Phase II anticipated to start later this summer.