Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook

Week of Sept. 7, 2021

City Projects

2021 Federal Resurfacing (Michigan Paving)

All main paving work is complete.  Contractor is working on small items – casting adjustment, topsoil, seed, signage.  Some lane closures will be placed when needed to complete work.

2021 Watermain Project - Dehoop, Michael, and Wadsworth (Wyoming Excavators) 

Dehoop is complete.

Michael is complete.   

On Wadsworth, the contractor is working on preliminary punchlist items. Top course asphalt is scheduled to be placed next week Monday.

2021 Watermain Project - Buchanan Ave. Watermain 40th - 44th (Nagel Construction) 

The contractor is finishing concrete placement today.  The contractor will mill asphalt surface on Thursday, grade subgrade Friday and pave base course next week.

2021 56th Street Sanitary Sewer Project – Haughey Ave to Division Ave (Diversco Construction)

Contractor has been dewatering in the area in preparation to start laying sanitary sewer.  Contractor will start laying main on Monday and continue throughout the week.  Dewatering is required ahead of the placement of sanitary main as the contractor works down 56th Street.

Plats

Rivertown Valley Plat Phase 5 – The contractor is working on private utilities outside the right of way. The contractor is waiting to address punchlist items. 

Rivertown Valley Plat Phase 6 – The contractor is working on building construction

Greens of Wyoming Phase 2 – The contractor poured the large retaining wall. The contractor can focus on street grading next. 

Albright Estates Phase 2 – The contractor has graded the site in preparation for construction.