Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of June 9, 2025
CITY OF WYOMING PROJECTS​
Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)
Pavement has been removed on Division Avenue from 44th Street to Bellevue Street (Phase 1).  Division is open to local businesses, but closed to through traffic.  The best way to access businesses is from side streets.  Contractor is working on connecting watermain to side streets and water services to individual businesses.  Reconstruction of the street has started in Phase 1: Contractor is grading the street and placing the new gravel base.  Damaged concrete is being removed and new concrete placement is planned to start next week. Base course paving of Phase 1 is anticipated to be done by the end of June.
Watermain installation on Maplelawn is complete and has passed all testing.  Watermain tie- ins and waterservices on Maplelawn are planned for this week.

Division Ave looking South

Division Ave looking North

Division Ave Phasing Plan
Wyoming City Center Bridge Project (Anlaan Construction)
The contractor is working on the pedestrian bridge over 28th Street. Contractor is working on installation of architectural panels. Periodic lane closures on 28th Street will be required for this work.
Wyoming City Center Trail Project (Katerberg-Verhage and Strain Electric)
Trail work continues in Pinery Park. HAWK signal work will continue in late summer when strain poles are available.
PRIVATE DEVELOPMENT PROJECTS
Benteler Automotive Fireline (4011 Stafford Ave., SW) – Dan Hoe Excavating
Utility work in 40th Street is complete, Contractor plans to patch the street today.
Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.
Right Turn lane and traffic signal on 36th Street not yet scheduled.
Godwin Mercado (36th St. Market) Watermain – GVL Excavating
Remaining drive approach on 36th Street is planned in the next couple weeks.
Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating
Contractor is working on storm sewer with road construction to follow. Storm sewer work has been slowed due to utility conflict. Entrance on Buchanan is planned to start in a couple weeks and will require a lane closure.
Malta Woods (N. off 56th, E of Wilson) – Fischer Idema
Contractor is working on placing concrete within the plat. Storm sewer connection in 56th Street is not yet scheduled.
Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating
Contractor is working on grading for the streets within the plat.
Courtyard at Wyoming (4051 Del Mar Drive) – Excel Excavating
Watermain and Sanitary Sewer construction is expected to start in a few weeks. This work will require lane closures on Del Mar Drive.