Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of July 7, 2025
CITY OF WYOMING PROJECTS​
Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)
Contractor is working on lawn restoration in phase 1.
Approximately 2/3rds of the watermain has been installed in phase 2. Watermain work will continue this week.

Division Ave Phasing Plan

Watermain Installation

Phase 1 Pavement with temporary striping
Wyoming City Center Bridge Project (Anlaan Construction)
The contractor is working on the pedestrian bridge over 28th Street. Contractor is working on installation of architectural panels and lighting components. Periodic lane closures on 28th Street will be required for this work.
Wyoming City Center Trail Project (Katerberg-Verhage and Strain Electric)
Trail work continues in Pinery Park. HAWK signal work will continue in late summer when strain poles are available.
PRIVATE DEVELOPMENT PROJECTS
Benteler Automotive Fireline (4011 Stafford Ave., SW) – Dan Hoe Excavating
Final watermain connection at 40th and Stafford planned for this week. This will finish work on all City Utilities.
Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.
Right Turn lane and traffic signal on 36th Street not yet scheduled.
Godwin Mercado (36th St. Market) Watermain – GVL Excavating
Remaining drive approach on 36th Street is planned in the next couple weeks dependent on relocation of a Consumers Energy pole.
Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating
Contractor plans to pave base course of asphalt this week, which will require a lane closure on Buchanan Avenue. Base course will be paved around conflicting utility pole. Top course of asphalt won’t be scheduled until Consumers Energy pole is relocated. This is anticipated to be several weeks out.
Malta Woods (N. off 56th, E of Wilson) – Fischer Idema
Contractor is working on placing concrete within the plat and is nearly finished. Storm sewer connection in 56th Street is not yet scheduled and is dependent on fiber optic lines being relocated by AT&T. This schedule is at least 2-3 weeks out.
Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating
Contractor is removing excess soil from the plat and working on placing gravel for new streets.
Courtyard at Wyoming (4051 Del Mar Drive) – Excel Excavating
Sanitary sewer connection is complete and Del Mar Drive has been re-opened. Watermain connection is planned for this week.