Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook

Si necesita esta informaciĂłn traducida al español, comunĂ­quese con nuestra oficina al (616)530-7260. 

City Projects

Week of August 17, 2026

CITY OF WYOMING PROJECTS

Burton Street Reconstruction - Burlingame to Clyde Park (including work on Osmer) (Anlaan Corp)

Burton between Kamp Avenue and Clyde Park Avenue:

  • Contractor is working on placing remaining concrete items
    • Some locations cannot be poured until Consumers moves poles
  • Contractor is also working on lawn restoration

Burton between Burlingame Avenue and Kamp Avenue:

  • Testing for first segment of watermain (Kamp to Martindale) will occur this week
  • Contractor is continuing to place the second segment of watermain from Martindale to Burlingame
  • Local traffic will be maintained in the west bound direction only in this section.

Osmer Avenue:

  • Contractor has some lawn restoration and clean-up left to be completed.

Boone Avenue Watermain Reconstruction - Lacrosse to 36th Street (Wyoming Exc)

Contractor plans to complete paving of the street this week, weather dependent.

56th Street and Byron Center Dual Left Turn Lane - (Brenner Exc)

Northbound left lane on Byron Center will remain closed for several weeks. Contractor has placed the base course for the new lane on 56th Street and is working on pouring the concrete sidewalk.

Wyoming Local Resurfacing Program - (Michigan Paving and Materials, Inc)

Havana Avenue between Lee Street and Chicago Drive:

  • This segment is complete

Palm Dale, Cotton Dale, Pine Slope and Naples Cedar Area:

  • Contractor plans to begin concrete removal this week.

Prairie Parkway Reconstruction – Wentworth to Michael - (Wyoming Exc)

Prairie between Michael and Burlingame:

  • Contractor plans to complete top course paving and pavement markings.
  • Contractor is also working on traffic signal modifications and completing remaining concrete work.
  • This segment of the project is scheduled to be completed prior to the first day of school on August 25.

Prairie between Byron Center and Wentworth:

  • Watermain installation between Byron Center and Nursery is complete and scheduled to be tied-in this week.
  • Traffic will be maintained in the eastbound direction.

 

PRIVATE DEVELOPMENT PROJECTS

3738 – 52nd Street - Salmon’s View Residential Development (Excel Exc)

Utility work in 52nd Street is complete. Contractor will have some shoulder work to do next week which will require short term flagging operations.

300 36th Street – Corewell Heath (Pioneer Construction)

Contractor has completed pavement markings. Date for activation of the new signal has not been set.