Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of September 15, 2025
CITY OF WYOMING PROJECTS​
Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)
Phase 1 is complete except for minor clean-up and top course paving. Installation of new streetlights is in progress.
Phase 2: is complete except for minor clean-up and top course paving. Installation of new streetlights is in progress.
Phase 3 Contractor will finish watermain installation this week and start watermain testing. Concrete removal have started and will continue this week.

Division Ave Phasing Plan
Wyoming City Center Bridge Project (Anlaan Construction)
The contractor is working on the pedestrian bridge over 28th Street. Contractor is working on final details for bridge opening planned for September 27.
Wyoming City Center Trail 7 (Wyoming Excavators)
Contractor is working on finishing concrete on Godfrey and will start asphalt patching. They will move to Belfield Street between Clyde Park and Roos later this week.
Wyoming City Center Trail Project (Katerberg-Verhage and Strain Electric)
Trail work continues in Pinery Park. Final items to complete the HAWK signal work on DeHoop are expected this week.
Burlingame Avenue Resurfacing – 36th St. to 52nd St. (Rieth-Riley)
Resurfacing work begins today. The outside lanes will be closed and all traffic will shifted to the inside lanes.
2025 Cape Seal Pavement Preservation Project (Strawser Construction)
Project is complete except for some minor clean up. Contractor will return in mid-September to repair wheel marks in the surface.
PRIVATE DEVELOPMENT PROJECTS
Buchanan Ave Railroad Crossing (South of Plaster Creek) – Grand Elk Railroad
The Grand Elk Railroad will be replacing the railroad crossing of Buchanan Avenue starting today. This work will take approximately 2 weeks to complete. Buchanan Ave will be closed and traffic will be detoured to Division Avenue using 28th Street and Burton Street.
Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.
Contractor is working on Right Turn lane and traffic signal on 36th Street. East Bound curb lane will be closed on 36th Street from Clay to Buchanan and will remain closed for a couple weeks. Consumers Energy Poles are in conflict with this work and relocation schedule is unknown. Gas main conflict has been resolved.
Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating
Utility pole relocation is complete. Final paving on Holdwood has not yet been scheduled. The Southbound curb lane of Buchanan will have intermittent closures at Holtwood Street.
Malta Woods (N. off 56th, E of Wilson) – Fischer Idema
Storm sewer connection in 56th Street is planned for this week. Remaining work in 56th Street will require a short duration detour and also a lane closure and flagging.
Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating
Base course paving is complete. Contractor will be working on raising castings and correcting some grading issues this week.
Courtyard at Wyoming (4051 Del Mar Drive) – Excel Excavating
Utility connections are complete. Installation of drive approaches has not yet been scheduled.