Weekly Update

Infrastructure Investments and Construction Activities

Week of May 20, 2019

CITY PROJECTS

2018 Wyoming Resurfacing (Michigan Paving and Materials)

Wet weather continues to affect work.  Contractor paved base course on Lee Street and Mulligan Ct, and Bunkerway last week.  Belfield, Banner and Roos scheduled for base course paving on Monday.  Pave top course on all streets late this week and/or next week.  Contactor to complete topsoil and seed restoration all locations prior to finalizing project.

Clyde Park Watermain, 26th St to 36th St (Nagel Construction)

Pre-construction meeting scheduled for Wednesday.  Start construction May 27.

54th Street Widening, Haughey to US-131

Project is on the July MDOT bid schedule and August award.  Construction of the bridge work will likely not be complete in 2019 due to a long bridge beam fabrication timeframe.  Additional lane will be constructed in 2019 and function as a right turn only onto Clay Ave until bridge work can be completed.

Interurban Trail Rehab (Epic Excavating)

Project will start in late May.  Completion date is August 31.

Frog Hollow M-6 Trail Connector

Revised project design and trail easements.  Updating plan to include Grade Inspection comments. Prepping final MDOT package for bidding.  Project is scheduled to be in the September MDOT letting with October construction.

2019 Wyoming Resurfacing

Assembling streets and plan quantities to assemble bid package.  Anticipate bidding in June for construction in later summer.

 

PLATS

Reserve Plat Phase 4 (Kentwood Excavating)

Contractor working on sanitary laterals and water services in existing Nile Drive.  Engineer revised plan for sewer reconstruction in Nile Dr. opposite existing homes. 

Greens of Wyoming (B and R Excavating)

Contractor continuing working on sanitary sewer and also on storm sewer.  Site soils slow work down in wet weather. 

Buck Creek Hill Estates (Caledonia Excavating)

Contractor building street cross section – curb and gutter is complete and contractor grading gravel prepping for base course pavement.

Chapel Estates (Caledonia Excavating)

Watermain is tied in and contractor is starting tapping water services this week.  Open all lanes of Burlingame once patch is paved.

 

SITE DEVELOPMENTS

Clyde Park 2-Hotels

Plan requires median modification for new LT lane into site.  New signals for new westerly leg of intersection at 58th St and Clyde Park.

MHV Unit 4

Finalizing City/developer storm sewer agreement.  Bids due Monday to re-route existing storm outlet.

MHV Credit Union

Currently prepping site.  Connection to sanitary sewer in Gezon Parkway and watermain may require lane closures in Gezon.

MHV PUD Update Plan (ODP)

Starting to update traffic impact study for site and surrounding intersections to accurately account for proposed development.

Springs Apartments

Start in June.

The Apartments at 28 West

Waiting for construction plans. Start construction later in summer.