Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of August 26, 2025
CITY OF WYOMING PROJECTS​
Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)
Phase 1 is complete except for minor clean-up and top course paving.
Phase 2: Contractor plans to pave base course this week.
Phase 3 Contractor is working on watermain installation and plans to finish mainline by the end of next week.


Waterservice Installation


20” watermain installation

Division Ave Phasing Plan
Wyoming City Center Bridge Project (Anlaan Construction)
The contractor is working on the pedestrian bridge over 28th Street. Contractor is working on installation of architectural panels and lighting components. Periodic lane closures on 28th Street will be required for this work.
Wyoming City Center Trail 7 (Wyoming Excavators)
Construction of new 10’ side path is expected to start this week. Contractor plans to start on Godfrey Avenue, south of Burton.
Wyoming City Center Trail Project (Katerberg-Verhage and Strain Electric)
Trail work continues in Pinery Park. HAWK signal work will continue in late summer when strain poles are available.
Burlingame Avenue Resurfacing – 36th St. to 52nd St. (Reith-Riley)
Resurfacing work is expected to begin Tuesday after Labor Day
2025 Cape Seal Pavement Preservation Project (Strawser Construction)
Project is complete except for some minor clean up. Contractor will return in mid-September to repair wheel marks in the surface.
PRIVATE DEVELOPMENT PROJECTS
Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.
Contractor is working on Right Turn lane and traffic signal on 36th Street. East Bound curb lane is closed on 36th Street from Clay to Buchanan and will remain closed for a couple weeks. Consumers Energy Poles are in conflict with this work and relocation schedule is unknown.
Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating
Consumers Energy is working on pole relocation to allow top course of asphalt to be placed. The Southbound curb lane of Buchanan is closed at Holtwood Street.
Malta Woods (N. off 56th, E of Wilson) – Fischer Idema
Storm sewer connection in 56th Street is not yet scheduled. This connection will require a lane closure and flagging on 56th Street.
Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating
Contractor placing curb and gutter for new streets and plans to begin paving later this week.
Courtyard at Wyoming (4051 Del Mar Drive) – Excel Excavating
Utility connections are complete. Installation of drive approaches has not yet been scheduled.