Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of October 20, 2025
CITY OF WYOMING PROJECTS​
Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)
Phase 1 is complete except for minor clean-up and top course paving.
Phase 2: is complete except for minor clean-up and top course paving. Installation of new streetlights is in progress.
Phase 3 All watermain work is complete. Contractor plans to complete concrete and topsoil this week and begin paving, weather permitting.

Division Ave Phasing Plan
Wyoming City Center Trail 7 (Wyoming Excavators)
Contractor is placing concrete path in Pinery Park along Dehoop Avenue. This will require a lane closure in DeHoop from Belfield to the south end of Pinery Park. He is also working on preparation for paving between Roos and Michael.
Wyoming City Center Trail Project (Katerberg-Verhage and Strain Electric)
Contractor is working to finish railings and lighting within Pinery Park.
Burlingame Avenue Resurfacing – 36th St. to 52nd St. (Rieth-Riley)
Paving is complete on the west half of Burlingame. Contractor plans to finish paving the east half of Burlingame this week. When paving is complete contractor will begin setting manhole castings in concrete collars which will require lane closures.
PRIVATE DEVELOPMENT PROJECTS
Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.
Contractor is working on Right Turn lane and traffic signal on 36th Street. This area has been paved but contractor still needs to place Pavement. Traffic signal installation has not yet been scheduled.
Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating
Final paving on Holtwood was delayed again and schedule is unknown. The Southbound curb lane of Buchanan will have intermittent closures at Holtwood Street.
Malta Woods (N. off 56th, E of Wilson) – Fischer Idema
Paving is complete and 56th Street is open to traffic. Contractor still needs to complete pavement markings and restoration of the bike path.
Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating
Paving is complete and contractor is working on raising castings.
Courtyard at Wyoming (4051 Del Mar Drive) – Excel Excavating
Drive approach on Ayreshire is complete. Drive approach on Del-Mar is planned for this week and a lane shift will be needed.