Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of Sept. 30, 2024
CITY OF WYOMING PROJECTS
Fisher Avenue, South of 54th Street (Schippers Excavating)
The contractor completed testing the new watermain and will connect to the system on Monday. The remaining week they will continue construction of the new road base and storm sewer construction. The project is anticipated to continue for another few weeks. Please use caution when accessing Fisher Avenue from 54th Street.
Wyoming Ave Watermain, 36th St to Lacrosse St – 2024 Watermain Replacement (Dykema Excavating)
The Contractor plans to finish the topsoil and hydroseed early in the week prior to milling the asphalt pavement on Wednesday. Thursday the contractor will prep for paving the base course of asphalt on Friday.
2024 Federal Resurfacing Project – Gezon Parkway/54th St Resurfacing (Rieth Riley)
The Contractor is working on completing punchlist items. The majority of the work is complete, but lane closures will be required in the work areas. Please use caution when traveling through the area as the work locations change.
2024 Federal Resurfacing Project – Clyde Park Ave – Kenowa Ave (Michigan Paving)
After the project was complete, a watermain break occurred and requires closure north of 56th Street to complete the repair. The contractor set dewatering pumps last week and will begin repairing the main starting Monday. It will likely be repaired by Wednesday and ready for pressure testing and chlorinating. Once passing, the contractor will begin the repair of the road. Final paving will be towards the end of next week.
2024 Wyoming Resurfacing Project (Michigan Paving)
The contractor plans to mill the asphalt pavement of Sentinal, Cranwood, and Woodhill on Tuesday. They will follow with paving the base course of asphalt on Wednesday. The remaining week they will begin raising castings in preparation for final paving. On Pinnacle and Mayflower, they are almost complete with concrete repairs and will begin lowering castings in preparation for milling the asphalt. The mill is not scheduled for this location yet. The contractor plans to start concrete removals on Ayrshire and Del Mar late this week.
GRAND RAPIDS CONSTRUCTION (adjacent to Wyoming City limits)
Ceazar Chavez, Clyde Park Ave to Hall Street
The contractor is has paved the street and is raising castings to finish grade. Traffic is detoured around the project.
Division Avenue at Plaster Ck Bridge
Grand Rapids has started concrete repairs on the Division Avenue median immediately south of the Plaster Creek bridge (north of 28th Street). Currently, work is being done with lane closures but the pavement repair will require a full closure of Division Avenue. Once started, traffic will be detoured.