Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on construction activity. Below you'll find updates for city projects, plats, and site developments. Check back each week for updates or follow us on Facebook

Week of June 14, 2021

City Projects

2020-2021 Wyoming Resurfacing (Rieth Riley)

Contractor has completed the concrete replacement on 32nd Street east of U.S. 131. Contractor will lower sewer hole casting in preparation for milling asphalt Tuesday. Paving is scheduled for Thursday. Burlingame/28th Street to Burton concrete repairs will continue this week. Traffic is reduced to one lane in each direction. Mill work is scheduled for June 21-22, with paving scheduled for June 24-25.

2021 Federal Resurfacing – Wilson Avenue (Michigan Paving)

Concrete repairs continue, with traffic reduced to one lane in each direction. New concrete is expected  next week.

2020 - 2021 Watermain Project – Denwood (Bultsma Excavating)

Contractor plans to mill the pavement Tuesday and then remove the remaining concrete on the east side. Contractor will pour new east side curb and gutter late this week – weather dependent – and pave the bike path Thursday.

2021 Watermain Project – Dehoop, Michael and Wadsworth (Wyoming Excavators) 

Dehoop (Burton to Belfield), Michael (40th to 44th), Wadsworth (Buchanan to Division) 

Contractor is working on concrete restoration on Denwood and laying water main from 44th Street north.   

2021 Watermain Project – Buchanan Avenue Water main 40th-44th (Nagel Construction)

Contractor plans to start construction Wednesday. Initially, crews will strip topsoil and saw cut curb and gutter for removal.

Plats

Rivertown Valley Plat Phase 5 – The turn lane paving will be incorporated into the Wilson Ave resurfacing contract above.  The plat paving of the top course of asphalt will occur in June, but is not scheduled at this time.

Greens of Wyoming Phase 2 – Contractor is working on the street grading and a large retaining wall. 

Site Developments

Grandville 7/8 Building Construction – Contractor working on private utilities.