Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook

Si necesita esta informaciĂłn traducida al español, comunĂ­quese con nuestra oficina al (616)530-7260. 

City Projects

Week of September 18, 2023 

Jordan, Calhoun, Opal and Loraine – 2023 Watermain Replacement (Bultsma Excavating)

All streets are complete.  A walkthrough of project and punchlist items remain.

2023 Wyoming Resurfacing Program - Various Locations (Reith Riley)

The contractor is working on concrete repairs on 38th Street, Cook and Cook Court, followed by Roys, Plastico and Milan. After repairing the concrete, manhole castings will be lowered in preparation for milling asphalt pavement.

Noel, Wykes and Longstreet – 2023 Watermain Replacement (Wyoming Excavating)

The contractor continues to connect water services to the new watermains. Service connections should be completed on Monday. The contractor is also completing watermain tie-ins to the water system. All watermain work should be complete this week. Concrete restoration work is planned to begin at the end of the month.

44th Street at Burlingame Avenue, Watermain Valve Replacement

The contractor is scheduled to start the valve replacement next week starting Monday (weather dependent).  All lanes have been opened on 44th Street until the start of the excavation.

Site Developments

Week of September 18, 2023

Wyoming Junior High School

Work on firelines and water services will start after the new building is further along in construction.

60th Street and Clyde Park Ave. (Penske Development)

The contractor has finished the sanitary work and has started on the storm sewer construction. Work on the storm sewer will continue for a week or more and then switch to watermain construction. 60th Street remains closed west of Clyde Park Ave. For access to 60th Street, please use Burlingame Ave.

The Retreat (NE Corner of 52nd Street and Byron Center Ave.) 

The contractor has cleared trees from the site and is stripping topsoil in preparation for mass grading.

MDOT

 

PLATS