Weekly Update

Infrastructure Investments and Construction Activities

Week of November 18, 2019

CITY PROJECTS

Clyde Park Watermain, 26th St to 36th St (Nagel Construction) 

Contractor completed the restoration of brick pavers and topsoil north of 28th St last week.  Contractor continuing to work on restoration of retaining walls between 32nd St and 36th St as weather allows.  Due to seasonal limitations, contractor plans to grade the top soil but wait to hydro-mulch until spring. 

54th Street Widening, Haughey to US-131 (Kamminga & Roodvoets) June 15, 2020 Completion

The contractor finished paving top course on 54th St on Saturday.  The project is open to traffic with some minor restoration work to complete.

2019 Wyoming Resurfacing (Reith Riley)

Contractor plans to pave the top course of asphalt on Boss St and Ariebill St on Wednesday this week.  The remaining streets in the project will resume in the spring of 2020.

 

SITE DEVELOPMENTS

Clyde Park 2-Hotels

New driveway opening and median left turn lane are complete.  The traffic signal modification will likely be completed in the spring of 2020. 

The Springs Apartments

Contractor plans to tie in the watermain connection on 56th St Monday.  This will require a lane closure and flagging operation during process. 

HOM Flats at 28 West

Contractor working on site grading and building foundations.