Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook

Si necesita esta informaciĂłn traducida al español, comunĂ­quese con nuestra oficina al (616)530-7260. 

City Projects

Week of April 28, 2025

CITY OF WYOMING PROJECTS

Division Avenue Watermain – 36th St to 44th St (including work on Maplelawn) (Dykema Excavating)

Pavement has been removed on Division Avenue from 44th Street to Bellevue Street. Street is open to local businesses, but closed to through traffic. The best way to access businesses is from side streets. Contractor is installing watermain, working from south to north.

Wyoming City Center Bridge Project (Anlaan Construction)

The contractor is working on the pedestrian bridge over 28th Street. Periodic Lane closures are planned on 28th Street. Curb and Gutter replacement is planned on Hook Avenue. This will restrict the street to 1 lane.

Wyoming City Center Trail Project (Katerberg-Verhage)

The contractor plans to pour ADA ramps on Dehoop Avenue and Newstead by the end of the week. Periodic daytime lane closures are planned for pouring concrete and utility work. Work on HAWK signal on Dehoop continues this week.

 

PRIVATE DEVELOPMENT PROJECTS

Benteler Automotive Fireline (4011 Stafford Ave., SW) – Dan Hoe Excavating

Watermain installation continues within the Benteler site.

Corewell Health Watermain & Fireline (300 – 36th St., SW) – Connan Inc.

Watermain testing to begin this week. Right Turn lane and traffic signal on 36th Street scheduled later this spring.

Godwin Mercado (36th St. Market) Watermain – GVL Excavating

Contractor has completed underground utility work. Drive approaches on 36th Street are planned in the next couple weeks.

Holtwood Street (old GM Plant off Buchanan Ave) – Dan Hoe Excavating

Watermain has been tied in. Contractor is working on storm sewer with road construction to follow.

Malta Woods (N. off 56th, E of Wilson) – Fischer Idema

Watermain passed all testing, tie-in not yet scheduled. Contractor plans to connect storm sewer in 56th Street in a couple of weeks.

Rivertown Valley Phase 7 (Reserve Drive/Nile Drive area) – Schippers Excavating

Contractor constructing storm and sanitary sewers.