Construction Activities and Infrastructure Investments
Each week, we'll update this page with the latest information on construction activity. You'll find updates for city projects, plats and site developments. Check back each week for updates or follow us on Facebook.
Si necesita esta informaciĂłn traducida al español, comunĂquese con nuestra oficina al (616)530-7260.
City Projects
Week of July 27, 2026
CITY OF WYOMING PROJECTS
Burton Street Reconstruction - Burlingame to Clyde Park (including work on Osmer) (Anlaan Corp)
Burton between Kamp Avenue and Clyde Park Avenue:
· Contractor is placing concrete curb and gutter and grading gravel.
· Plan to pave the base course at the end of the week
Burton between Burlingame Avenue and Kamp Avenue:
· Contractor will begin pavement removal this week in preparation for watermain replacement.
· Local traffic will be maintained in the west bound direction only in this section.
Osmer Avenue:
· Paving was completed last week.
· Contractor has some lawn restoration and clean-up left to be completed.
Boone Avenue Watermain Reconstruction - Lacrosse to 36th Street (Wyoming Exc)
Contractor has completed concrete and is working lawn restoration. Contractor will also work on preparing to repave the road, which is scheduled for next week.
56th Street and Byron Center Dual Left Turn Lane - (Brenner Exc)
Northbound left lane on Byron Center will remain closed for several weeks. Contractor will also continue utility and concrete work on the north side of 56th Street, from Byron Center to the west. This work will require a lane shift and the east bound to north bound left turn lane will be closed.
Wyoming Local Resurfacing Program - (Michigan Paving and Materials, Inc)
Contractor plans to complete concrete replacement on Havana Ave between Lee Street and Chicago Drive this week. They will begin removing manhole covers in preparation for pavement removal and repaving next week.
Prairie Parkway Reconstruction – Wentworth to Michael - (Wyoming Exc)
Contractor is working on “crush and shape” of the old pavement in the area between Michael and Burlingame. The north half of the road has had the base course paved. Traffic will be shifted today to run on the new pavement and traffic flow is in the West bound direction only. Contractor will be working on concrete bike path and curb and gutter on the south side.
Contractor plans to start on watermain replacement between Wentworth and Byron Center next week.
Cape Seal Pavement Preservation
The City's cape seal pavement preservation street surface treatment for the 2026 season is tentatively scheduled for the week of July 20.
A cape seal is a two-part pavement preservation process that improves, preserves, and extends the useful service life of an existing street surface.
Schedule
The project will last about two weeks, but is subject to change depending on weather, availability of materials, or unforeseen emergencies. Each street takes approximately two days.
Work will be completed Monday through Saturday, from 7 am to 9 pm. Expect “no parking” signs on applicable street segments. To avoid any inconvenience as work takes place, residents are encouraged to park on adjacent streets via on-street parking.
Project Locations
|
Street
|
Limits
|
|
Wyoming
|
Lee to Chicago Dr
|
|
Collingwood
|
Lee to Chicago Dr
|
|
Burton
|
Greenfield to Collingwood
|
|
Ithaca
|
Greenfield to Collingwood
|
|
Avon
|
Porter to North end of street
|
|
Melvin/Ithaca
|
Greenfield to East end of street
|
|
Lee
|
Sharon to Avon
|
|
Meurs Ct
|
Avon to West end of street
|
|
Wyoming
|
28th to Porter
|
|
Boulevard
|
Wrenwood to Porter
|
|
Wrenwood
|
Wyoming to Meyer
|
|
Avon
|
28th to Porter
|
|
Meyer
|
28th to Porter
|
PRIVATE DEVELOPMENT PROJECTS
3738 – 52nd Street - Salmon’s View Residential Development (Excel Exc)
Contractor is working on Site Grading. Utility work in 52nd Street is starting on Monday, July 27, and will require 52nd Street to be closed for approximately 2 weeks. Closure location is 3738 52nd Street, across from Grandview Elementary. Through traffic will be detoured to 56th Street via Wilson and Ivanrest. Local traffic can enter either from the east or the west: Alexandria area and the School will have access from Wilson. Salman River and Copper River areas will have access from Ivanrest
300 36th Street – Corewell Heath (Pioneer Construction)
Contractor had delayed pavement markings and new schedule is unknown. This work will require 1 lane in each direction to be closed.