Weekly Update

Construction Activities and Infrastructure Investments 

Each week, we'll update this page with the latest information on construction activity. Below you'll find updates for city projects, plats, and site developments. Check back each week for updates or follow us on Facebook

 
Week of September 28, 2020

City Projects

2020 Wyoming Resurfacing (Reith Riley)

Chalet Estates Area (Palmair, Pine Dunes, Fieldstone and others):  Contractor is working to complete concrete removals this week.  Rotomill is scheduled for Monday this week but is subject to weather.  Base course asphalt to follow milled areas the next day.  Mill and base paving anticipated to take one week in this neighborhood depending on weather

Royal Oak, Kentfield, Bryant, 35th, Kenneth, Herman, Bryant:  Contractor has finished paving in the area and working on topsoil restoration.

Buck Creek Nature Trail Parking Lot:  Mill and base course scheduled for Monday this week, or as weather allows.

Charlesgate:  Removals have been marked and work to begin this week.

Buck Creek Nature Trail Parking Lot:  Possibly start at the end of this week or early next.

2020 Watermain Project – Buchanan Ave, 36th St to 40th St (Bultsma Excavating)

The contractor has finished is placing new main across the 36th St intersection and is testing the new main prior to connecting to the system.  Test results are anticipated late in the week.  The contractor is working on side street watermain tie ins south along Buchanan along with water service connections to the new main.

2020 Watermain Project – Denwood & Marquette (Bultsma Excavating)

On Marquette, the contractor is complete with this project.   Denwood watermain reconstruction will push to 2021 due to seasonal limitations.

Byron Center Resurfacing, 44th Street to M-6 (Michigan Paving and Materials, Inc)

The contractor will flip the lane closure configuration early this week to have traffic run on the outer lanes while work begins on the median.  The contractor will start with removals on the median south of 44th Street.  Contractor will lower castings in preparation for the mill and repair other damaged curb and gutter in the median.  The concrete subcontractor is anticipated to pour curb repairs next week. 

New Burlingame Pump Station and Tank Restoration

The Burlingame east tank rehab continues.  

  • The East storage tank rehab is nearing completion.  The “door” is being welded back in place and the final paint being applied.
  • Exterior work has started on the West tank beginning with power washing and exterior repairs.

Bayberry Farms Stormwater Improvements (Katerberg - VerHage, Inc)

The contractor completed the main work of the Condo improvements and is working to finalize project restoration.  Work on the Scarsdale started last week with rough grading.  The contractor will final grade and work on restoration this week as weather allows.

 

Plats

Rivertown Valley Plat Phase 5 – The contractor is working on sanitary sewer laterals this week as weather allows.

 

Site Developments

Clyde Park 2-Hotels – Traffic signal modification work to start soon.

MHV PUD Update Plan (ODP) – On hold.