Construction Projects

Capital Improvement Program (CIP) 3-year implementation plan

2026 Construction Projects

Street Construction

  • Federally Funded Prairie Parkway Reconstruction, Road Diet and Watermain Replacement (Wentworth Drive to Michael Ave) 
  • Burton Street Reconstruction Road Diet and Watermain Replacement (Burlingame Ave to Clyde Park Ave) 
  • Byron Center Dual Left Turn Lanes at 56th St./Gezon Parkway 
  • 2026 Wyoming Resurfacing Project 

Watermain Construction

  • Boone Avenue, 36th Street to Lacross Street 
  • 39th Street, Division Avenue to Buchanan Avenue 
  • Osmer Avenue, Josten Street to Burton Street 

Sanitary Sewer Construction

  • Sanitary Sewer Lining – Various Locations

Non-motorized Construction

  • Federally Funded Prairie Parkway Non-motorized trail (Wentworth Drive to Michael Ave) 
  • Burton Street Non-motorized trail (Burlingame Ave to Clyde Park Ave) 

Preventative Maintenance

  • Bridge Epoxy
  • Crack Sealing

2027 Construction Projects

Street Construction

  • Federally Funded Resurfacing Project (Buchanan Avenue, 28th Street to Alger Street) 
  • 2027 Wyoming Resurfacing Project 
  • 44th Street Bridge over Buck Creek – Rehabilitation 

Watermain Construction

  • Holly, Buchanan and Florida, Division and 50th Street Area 
  • Woodward, Longstreet, Charlesgate and Highgate, 28th Street to 32nd Street 
    • 28th Street, Longstreet to Charlesgate 
    • Emma Ave, Burlingame to south end 
    • Daisy Lane, 28th Street to 29th Street 
    • Clay Court, Clay Avenue to north end  

Sanitary Sewer Construction

  • Sanitary Sewer Lining – Various Locations

Non-Motorized Trail Construction

  • Federally Funded Buchanan Avenue Non-motorized trail (28th Street to Alger Street) 

Preventative Maintenance

  • Bridge Epoxy
  • Crack Sealing

2028 Construction Projects

Street Construction

  • Federally Funded Resurfacing Project (Burlingame Ave, 52nd St to Gezon Pkwy) 
  • Federally Funded Resurfacing Project (36th Street, Clyde Park Ave to Division Ave) 
  • 2027 Wyoming Resurfacing Project 

Watermain Construction

  • Bellevue Street, Division Ave to Woodstock Ave 
  • Newport Street, Wyoming Ave to N. end 
  • Hazelwood Ave, 28th St to Newport St 
  • Boulevard Ave, 28th St to Wrenwood St 
  • Hague Ave, Porter St to 28th St 
  • Forest Grove Ave, 28th St to Lee St 
  • Central Ave, 28th St to Porter St 
  • Rockwood Ct, Wrenwood St to S. end 
  • Sharon Ct, Wrenwood St to S. end 
  • Clay Court, Clay Avenue to north end  

Sanitary Sewer Construction

  • Sanitary Sewer Lining – Various Locations

Non-Motorized Trail Construction

  • Federally Funded Burlingame Ave Non-motorized trail (52nd St to Gezon Pkwy) 

Preventative Maintenance

  • Bridge Epoxy
  • Crack Sealing